Project summary

Muchinda has carried out high-voltage line construction and substation installation works for ZESCO Limited since at least 2014, and is an appointed contractor under ZESCO's 2-year rate-based framework contract (Contract No. ZESCO/SS/008/2023-207) for small-scope distribution network construction, awarded October 2023.

Scope of works

  • Various 33kV and 11kV power line construction
  • Various 11kV switchgear and 11/0.4kV substation installations
  • Appointed contractor under ZESCO's small-scope distribution network lines (labour and transport) rate-based framework contract, October 2023

Outcome

ZESCO Limited confirmed prior line and substation works (reference letter, 2014). Muchinda appears as an appointed framework contractor (S/N 207) with a provisional two-year ceiling amount of K3,000,000.00 — a shared panel ceiling across all appointed contractors, not a value earned exclusively by Muchinda.